

Total Calls 2012 - 5
Jobs - 0
Pins - 0
January - 4
February - 1
Engine - 3
Squad - 0
Tanker - 3
Utility - 0
2011 - 75
Jobs - 5
Pins - 2
January - 2
February - 6
March - 4
April - 10
May - 3
June - 4
July - 4
August - 11
September - 13
October - 5
November - 6
December - 5
Engine - 28
Squad - 46
Tanker - 15
Utility - 14
2010 - 71
2009 - 76
2008 - 71
2007 - 72
2006 - 67
2005 - 62 |
|
February 2012 |
| S | M | T | W | T | F | S |
|---|
| | | | 1 | 2 | 3 | 4 | | 5 | 6 | 7 | 8 | 9 | 10 | 11 | | 12 | 13 | 14 | 15 | 16 | 17 | 18 | | 19 | 20 | 21 | 22 | 23 | 24 | 25 | | 26 | 27 | 28 | 29 | |
Members List:
 Webmaster: Jesse Shutt President: Robin Urich Vice President: Katina Schoffstall Secretary: Jesse Shutt Treasurer: David Faust Trustees: LeeAnn Bechtel Lonny Lenker Donald Shutt, Jr. Chief 216: Raymond Urich, Jr. (FFI) Chief 216-1: Robert Stoneroad (FFI) Chief 216-2: David Faust Captain 216: Troy Hoffman (FFI) Lt. 216: Andrew Snyder Photographer: William Bailey Firefighters: LeeAnn Bechtel Victoria Bunger Keith Casey Michelle Casey Carlton Chandler Matthew Danner Paul Enders, III (FFI) Jason Faust Matthew Faust (FFI) Travis Gladitsch Bruce Harman Kevin Johnston, Jr. John Koppenhaver (FFI) Mark Koppenhaver (FFI) Holly Landvater (First Responder) Lyle Lenker Lonny Lenker (FFI) Adam Maiden Jason Schoffstall Raymond Schreiber Tadd Shoop (FFI) Gary Stoneroad Mathew Stoneroad Kevin Urich Firefighter/EMT's: Jessica Enders (FFI) Jesse Shutt (FFI) Donald Shutt, Jr. Junior Firefighters: Kyle Bower Aren Faust Sean Kaufman Austin Kissinger Tyler Stoneroad Fire Police Captain: Robert Browning Fire Police 1st Lt.: Robin Urich Members: Vacant  Fire Police: Jean Bower Lavonne Browning Michelle Casey Martha Gruver Jessica Johnston Holly Landvater Jessica Maiden Michelle Myers Jason Schoffstall Katina Schoffstall Social Members: Carol Bunger Jeffrey Bunger, Sr. Alysha Danner Tandee Hoffman Brian Ranck Rodney Seiler Barbara Snyder Kimberly WeigandLinks Section
|  |
 New Building
 WEDNESDAY, JUNE 30TH, 2010
Today the floor in the social hall was finished. New flooring was also laid in both bathrooms. Only minor work remains until the renovations to the social hall and kitchen will be completed.
 Back half of the Social Hall floor now complete
 New floor in the Men's Restroom
SUNDAY, JUNE 20TH, 2010
Today members started laying the new wood laminate flooring in the main social hall. Members started at 08:30 hours and worked until 17:00 hours and got half of the floor laid. Also almost all of the painting in the social hall has been completed with only a few pieces of trim remaining to be painted.
 New wood laminate flooring
THURSDAY, MAY 6TH, 2010
Members are now starting to do some work in the social hall. Today the walls in the social hall were painted with primer along with the trim in the kitchen and the bingo room. Also the two brand new deep fryers were moved into the kitchen.
 Firefighter LeeAnn Bechtel is shown putting primer on the social hall walls
 The bingo room painted with primer
 The two brand new Deep Fryers in the Kitchen
THURSDAY, APRIL 29TH, 2010
Items are starting to be moved into the kitchen. The hand wash sink and 3-bay sink have been hooked up and are now working. The supression system has been finished and hooked up to the stove. A Class K Fire Extinguisher has been installed in the kitchen. The new convection oven has been moved into the kitchen and the cooler, freezer, fire company fridge and warmer have been moved back into the kitchen.
 Hand wash Sink and 3-Bay Sink
 Supression System hooked up to the stove
 Class K Fire Extinguisher installed in the kitchen
 Convection Oven in the Kitchen
 Cooler, Freezer, Fire Company Fridge and Warmer in the Kitchen
WEDNESDAY, APRIL 21ST, 2010
Work is slowly starting to wind down on the social hall. Today steps were built and installed for the new back door in the kitchen. Also in the kitchen the new tiles have been installed in the drop ceiling and the floor has had an expoy painted on it.
 New steps outside of back door in kitchen
 New drop ceiling tiles installed
 Expoy coating on floor in kitchen
SUNDAY, APRIL 18TH, 2010
Today a work detail was called to work on the social hall. All available members showed up and started working on the social hall. A floor was laid in the back room in the space where the boiler used to be. Everything was moved out of the bingo room and everything was moved away from the wall in preparation of painting the walls. Spackling was done on the walls in the social hall and the bingo room. The baseboard heaters were removed from the social hall and the bathrooms and the shutters were removed from the outside of the social hall.
 New floor in back room
 Bingo room cleared out and walls spackled and ready for primer
THURSDAY, APRIL 15TH, 2010
Work has been busy at the social hall the past few days. The new roof has been put on the main social hall. New light/exhaust fans have been installed in both bathrooms. A mop sink has been installed in the back room and a water filtration system has also been installed. New drop ceiling tiles have been installed in the main social hall. On the outside of the hall the exhaust vent for the hood system has been completed. In the kitchen the supression system is starting to take place for the hood system.
 New Roof on Mail Social Hall
 New Lights/Exhaust Fans in Mens Bathroom
 Mop Sink in Back Room
 Water Filtration system in Back Room
 New Drop Ceiling in Main Social Hall
 Pull Station for Supression System in Kitchen
 Tank for the Supression System in the Kitchen
 Outside Vent for Hood System
TUESDAY, APRIL 6TH, 2010
Work is starting to pick up on the social hall. The new rubber roof was placed over the kitchen today. Also the outside vent for hood system in the kitchen is starting to be installed. Also outside emergency lighting has been placed above each door and outside lighting has been installed in the one corner of the building. Inside the social hall exit signs and emergency lighting has been installed and wired in the main social hall. New lights are starting to be installed in the hall and a new light has been installed in the bingo room. In the womens bathroom a new baby changing station has been installed.
 Outside vent for hood system
 Emergency Light above side door
 Emergency Light above rear door in kitchen
 Emergency Light above front door
 New outside lights
 New light installed in bingo room
 New Emergency Lighting in social hall
 New Exit Sign above front doors
 New Exit Sign above side door
 New Baby Changing Station in Womens bathroom
FRIDAY, APRIL 2ND, 2010
Extensive work still continues in the kitchen and the social hall. In the kitchen the hood has been installed along with the new window in the back room. Trim has been placed around the enlarged serving windows and the stainless steel counter top covers have been fastened down. In the boiler room, the new tank less water heater has been installed. Also outside of the social hall the new propane tank from Koppy's Propane has been delivered and the gas lines have been laid and the tank less hot water heater and the new HVAC unit have already been hooked up.
 Hood installed in Kitchen
 New window in rear of Kitchen
 New trim around the serving windows
 Outside portion of new HVAC Unit installed and hooked up
 New Propane tank
 Tank less hot water heater installed in boiler room
TUESDAY, MARCH 30TH, 2010
Work continues in the kitchen. The new lights have been installed and wired in the ceiling and the new exit sign has been installed and wired in the rear of the kitchen.
 Exit Sign and Emergency Lighting in rear of Kitchen
 New ceiling lights in kitchen
MONDAY, MARCH 29TH, 2010
Work continues on both the kitchen and the social hall. In the kitchen the new grid work is being installed for the new drop ceiling. Also the covers for the electrical outlets have been installed. Outside the social hall a platform has been installed to hold the HVAC unit and piping has been run from the unit in the attic outside and down to the platform.
 New Grid Work in Kitchen
 Electrical Outlet Covers
 Outside platform for new HVAC Unit
 Piping for outside HVAC Unit
THURSDAY, MARCH 25TH, 2010
Work continues on the HVAC system in the social hall. Up in the attic the duct work has been laid out and the flex tubing has been laid out also.
 Duct work laid out in attic
FRIDAY, MARCH 19TH, 2010
Work continues on both the kitchen and the social hall. In the kitchen stainless steel caps have been made for the counter tops at the serving windows and have been test fitted. In the social hall work continues on the HVAC system. Ducts have been pre-feed in the main social hall and ducts and vents have been installed in both bathrooms.
 Stainless Steel Caps for Serving Window Counters
 Ducts Pre-Feed in Main Social Hall
 Vents Installed in the Bathrooms
TUESDAY, MARCH 16TH, 2010
Work continues on the HVAC system in the attic of the social hall with the duct work starting to be laid out and installed and ceiling vents being put in place.
 Vent hole in social hall ceiling
FRIDAY, MARCH 13TH, 2010
Work continue in the kitchen with the installation of the stainless steel wall panels for the hood system and the installation of the glass board wall coverings.
 Stainless Steel Wall Covering for Hood System
 Glass Board wall Covering
WEDNESDAY, MARCH 10TH, 2010
Today work continued on the kitchen and social hall. In the kitchen the new concrete floor was laid and the new double doors were installed in the rear of the back room. In the social hall, new steps were poured outside of the rear door to the social hall and the replacement windows were installed in the main hall, kitchen and bathrooms.
 New double doors installed in back room
 Replacement windows being installed
 New concrete floor in kitchen
 New concrete floor in kitchen
TUESDAY, MARCH 9TH, 2010
Lehman's was back at the social hall for the second day in a row. Today the finished installing and wiring the new lights and electrical outlets in the attic and started connecting the HVAC units together.
 New lights installed in attic
 New HVAC Unit
MONDAY, MARCH 8TH, 2010
Work continues on the social hall. Lehman's was there today and enlarged the opening in the social hall ceiling into the attic and the new HVAC units was moved up into the attic.
 Larger access hole into attic
FRIDAY, MARCH 5TH, 2010
Work continues on both the kitchen and social hall. In the kitchen drywall has been placed over in the hole where the window used to be. The rear wall in the back room has been prepared for the delivery and installation of a new set of double doors next week. Also prep work has started for anticipated pouring of the concrete floor in the kitchen next week. In the social hall the concrete steps at the rear door have been removed and forms are in place for concrete to be poured next week also.
 New drywall in back room
 Rear wall prepared for installation of new doors
 Form for the new back steps
WEDNESDAY, FEBRUARY 24TH, 2010
Work continues on both the kitchen and the social hall. Today the sub panel was installed in the kitchen and a new roof was laid over the bathrooms. Shingles were also installed on the overhang above the front doors. We decided to go with shingles for the roof over the bathroom to replace the tin roof.
 Sub panel in the kitchen
 New roof over the bathrooms
 New shingles on overhang of front doors
TUESDAY, FEBRUARY 23RD, 2010
Renovations continue with the window in the hall that went into the rear storage room removed and the hole in the wall enclosed in. Water lines were run in the kitchen and various parts of the social hall floor are being repaired also.
 Where the window used to be
 Hole in kitchen wall waiting to be covered up
 Water lines that have been run in the kitchen
MONDAY, FEBRUARY 22ND, 2010
Renovations on the social hall kitchen officially started today with the enlargement of the serving windows.
 Serving Window after being Enlarged
 Serving Window after being Enlarged
FEBRUARY 2010 - RENOVATIONS BEGIN
Renovations are ready to begin on the kitchen in the social hall within the next few days. Once the kitchen in the social hall is done, renovations will be done to the actual social hall. On Thursday, February 18th, 2010, members spent all afternoon and into the early evening moving stuff out of the kitchen and the back storage room and then did demolition work in both rooms which also included removing the wall that seperated both rooms.
 Firefighter LeeAnn Bechtel removes tracking for the old drop ceiling
 Chief 216 Raymond Urich, Jr., uses a chainsaw to make some cuts in wood on the wall prior to members removing the entire wall
 Firefighter Kevin Johnston, Jr., uses a sledge hammer to remove part of the cinder block wall seperating the kitchen and the back storage room
 View after demolition, looking towards Route 225
 View after demolition, looking towards Church Street
June 2008
A Building Fund Thermometer has been erected in the front lot along the side of the road. Please pay attention to this thermometer to see how our progress is doing. Special Thanks to Bev Heim for painting the number amounts and building fund on the sign.
 Building Fund Thermometer
April 2008
At April's Meeting we met with reprsentatives from Mid Penn Bank and USDA to discuss us applying for a USDA Loan and a loan with Mid Penn Bank. The application process with USDA will be starting soon.
March 2008
At March's meeting, plans were set forth and a meeting has been set up for sometime in April for the building committee to meet with a reprsentative from Mid Penn Bank and a representative from the USDA in regards to starting the application process for getting a loan from the USDA for the construction of the new station/hall.
February 2008
Our efforts at constructing a new station/hall are slowly but surely moving foward. The plans have been drawn up and a building committee was just put together and are currently checking on prices. Look for our fund raising efforts to increase in the next few years as we work towards making money to put towards constructing this new station/hall.
A little information regarding our current buildings. Our Fire Station was built in 1979 and we have now out grown this station. We have 3 pieces of apparatus housed in a 2 bay fire station. Our Fire Hall was built in the late 1800's and used to be the town shirt factory. We purchased the building in the 1950's and the kitchen was added in 1966. We have also out grown this building. The third building is the Old Fire House, which we now use as storage. Again we have outgrown this building and have very little space left in this building.
With the company looking to build the new station/hall, we wish to be able to combine everything from the current 3 buildings under one roof, while also providing additional space for the company to grow into the future. Please check back often for updates on the building. |